Project Name |
Development of Six Lane access controlled Greenfield Highway From Vankarakunta (Km.45+700)- Odulapalle (Km.72+00) of [NH-544G] Bengarulu-Vijayawada Economic corridor on HAM Mode under Bharatmala Pariyojana Phase-I in the State of Andhra Pradesh (Package-3). |
NH No. (New/old) |
544-G |
Scheme/Phase |
Bharatmala Pariyojana Phase-I |
Mode of Execution |
HAM |
No. of Lanes/Configuration |
6-Lane |
No. Of Bypasses(Name of Town, Length) |
Nil |
No. Of Major Bridges |
2 |
No. Of Minor Bridges |
10 |
No. of Hume pipe culverts |
10 |
No. of Box culverts |
41+10 |
No. of Box structure |
21 |
No. of Elevated Viaducts |
Nil |
No. of FOB |
Nil |
No. of ROB |
1 |
No. of Underpasses |
14 |
Toll Plaza |
1 |
Concessionaire Name |
M/s. Raj Path Infracon NH-544G Package-3 Private Limited |
Date of Letter of award(LOA) |
31.01.2023 |
Appointed Date |
02.03.2024 |
Construction Period (in Days) |
730 Days from the Appointed Date |
Schedule Completion Date |
01.03.2024 |
Operation & Maintenance Period |
15 years commencing from COD |
Independent Engineer |
M/s Dhruv Consultancy Services Ltd., Joint Venture with G-Eng. Advisory Services Pvt. Ltd. Associate with Kaius Consulting Pvt., Ltd., |
Authority Name |
NATIONAL HIGHWAYS AUTHORITY OF INDIA |