| Project Name | Development of Six Lane access controlled Greenfield Highway From Vankarakunta (Km.45+700)- Odulapalle (Km.72+00) of [NH-544G] Bengarulu-Vijayawada Economic corridor on HAM Mode under Bharatmala Pariyojana Phase-I in the State of Andhra Pradesh (Package-3). |
| NH No. (New/old) | 544-G |
| Scheme/Phase | Bharatmala Pariyojana Phase-I |
| Mode of Execution | HAM |
| No. of Lanes/Configuration | 6-Lane |
| No. Of Bypasses(Name of Town, Length) | Nil |
| No. Of Major Bridges | 2 |
| No. Of Minor Bridges | 10 |
| No. of Hume pipe culverts | 10 |
| No. of Box culverts | 41+10 |
| No. of Box structure | 21 |
| No. of Elevated Viaducts | Nil |
| No. of FOB | Nil |
| No. of ROB | 1 |
| No. of Underpasses | 14 |
| Toll Plaza | 1 |
| Concessionaire Name | M/s. Raj Path Infracon NH-544G Package-3 Private Limited |
| Date of Letter of award(LOA) | 31.01.2023 |
| Appointed Date | 02.03.2024 |
| Construction Period (in Days) | 730 Days from the Appointed Date |
| Schedule Completion Date | 01.03.2024 |
| Operation & Maintenance Period | 15 years commencing from COD |
| Independent Engineer | M/s Dhruv Consultancy Services Ltd., Joint Venture with G-Eng. Advisory Services Pvt. Ltd. Associate with Kaius Consulting Pvt., Ltd., |
| Authority Name | NATIONAL HIGHWAYS AUTHORITY OF INDIA |