Welcome To PKG-3

Development of Six Lane access controlled Greenfield Highway From Vankarakunta (Km.45+700)- Odulapalle (Km.72+00) of [NH-544G] Bengarulu-Vijayawada Economic corridor on HAM Mode under Bharatmala Pariyojana Phase-I in the State of Andhra Pradesh (Package-3).

697.21 Cr

Bid Project Cost

6-Lane

No. Of Lanes

730 Days

Construction Period

1

Toll Plaza

  • 29.08.2024

    Project Milestone-I

    180 (Days from Appointed Date )
    20%(progress)

  • 02.03.2025

    Project Milestone-II

    365 (Days from Appointed Date )
    35%(progress)

  • 18.09.2025

    Project Milestone-III

    565 (Days from Appointed Date )
    75%(progress)

  • 01.03.2026

    Schedule Completion Date

    730 (Days from Appointed Date )
    100%(progress)

CONNECT WITH US

Let's get in touch

We're open to any suggestion or just to have a chat.

020 2563 6060
Raj Path Infracon Pvt. Ltd. Amar Business Zone, C-Wing Office nos. 1302,3 & 4 Ganraj Chowk, Veerbhadra Nagar Baner, Pune 411045

All fields are mandatory

Thank You! We will get back to you soon.

premium bootstrap themes